Wang Wei, Liu Dong, Cui Xinhao, Li Bo, Xiao Yiyong, Ren Yi. Multi-level Digital Model of Dynamic Earned Value Management for Complex Engineering Projects and Its Applications[J]. Journal of System Simulation, 2026, 38(5): 1350-1364.
Table 1
Integrated manufacturing process project plan information for a certain aviation component
| 工作项 | 项目/工作项名称 | 工期计划/d | 成本计划/万元 | 工程资源计划 | |||
|---|---|---|---|---|---|---|---|
| 资源名称 | 数量 | 单价/元 | 总价/万元 | ||||
| 1 | 某器组件一体化制造工艺设计项目 | 150 | 8.4 | 管理人工r1/工时 | 1 200 | 55 | 6.600 |
| 办公设施r2/d | 150 | 120 | 1.800 | ||||
| 1.1 | 图纸与工艺设计 | 50 | 5.22 | 设计人工r3/工时 | 720 | 45 | 3.240 |
| 设备A折旧r4/d | 50 | 95 | 0.475 | ||||
| 能源动力费r5/万元 | 1.5 | 10 000 | 1.500 | ||||
| 1.2 | 样品加工 | 60 | 6.42 | 车间1人工r6/工时 | 480 | 38 | 1.820 |
| 材料A r7/kg | 100 | 150 | 1.500 | ||||
| 材料B r8/kg | 5 | 345 | 0.170 | ||||
| 设备B折旧r9/d | 60 | 122 | 0.730 | ||||
| 能源动力费r5/万元 | 2.2 | 10 000 | 2.200 | ||||
| 1.3 | 试验测试 | 40 | 5.03 | 试验人工r10/工时 | 720 | 38 | 2.730 |
| 设备C折旧r11/d | 40 | 85 | 0.340 | ||||
| 油料A r12/kg | 385 | 12 | 0.460 | ||||
| 能源动力费r5/万元 | 1.5 | 10 000 | 1.500 | ||||
Table 2
Actual progress and cost information at the project progress time (t=70 d)
| 工作项 | 项目进展时刻 | 工程资源实际消耗 | ||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
计划 进度/ % | 计划 成本/ 万元 | 实际 进度/ % | 实际 成本/ 万元 | 挣得 值/ 万元 | 成本 绩效 CPI | 进度 绩效 SPI | 资源 编号 | 计划 数量 | 消耗 数量 | 资源 成本/ 万元 | 挣得 资源/ 万元 | 成本 绩效 CPI | 资源 效用 RUI | |
| 1 | 47 | 3.92 | 47 | 4.41 | 3.92 | 0.91 | 1.0 | r1 | 560 | 595 | 3.34 | 3.08 | 0.92 | 0.94 |
| r2 | 70 | 81 | 0.97 | 0.84 | 0.86 | 0.86 | ||||||||
| 1.1 | 100 | 5.22 | 100 | 5.61 | 5.22 | 0.93 | 1.0 | r3 | 720 | 760 | 3.49 | 3.24 | 0.93 | 0.95 |
| r4 | 50 | 52 | 0.52 | 0.48 | 0.91 | 0.96 | ||||||||
| r5 | 1.5 | 1.6 | 1.60 | 1.50 | 0.94 | 0.94 | ||||||||
| r6 | 160 | 190 | 0.79 | 0.36 | 0.46 | 0.51 | ||||||||
| r7 | 33.3 | 56.0 | 0.92 | 0.30 | 0.32 | 0.36 | ||||||||
| 1.2 | 33 | 2.14 | 20 | 2.68 | 1.28 | 0.48 | 0.60 | r8 | 1.7 | 1.4 | 0.05 | 0.03 | 0.69 | 0.71 |
| r9 | 20 | 20 | 0.26 | 0.15 | 0.56 | 0.60 | ||||||||
| r5 | 0.70 | 0.65 | 0.65 | 0.44 | 0.68 | 0.68 | ||||||||
| 1.3 | 0 | 0 | 0 | 0 | 0 | r10 | 0 | 0 | 0 | 0 | ||||
| r11 | 0 | 0 | 0 | 0 | ||||||||||
| r12 | 0 | 0 | 0 | 0 | ||||||||||
| r5 | 0 | 0 | 0 | 0 | ||||||||||
| 总体 | 11.28 | 12.7 | 10.42 | 0.82 | 0.92 | 总体 | 1617.2 | 1757.65 | 12.59 | 10.42 | 0.73 | 0.75 | ||
Table 4
Work item constraint relationship
| 约束关系 | 工作项约束关系 |
|---|---|
| 包含关系集Γ | (1,6) (1,7) (1,8) (1,9) (1,10) (2,11) (2,12) (2,13) (2,14) (3,15) (3,16) (3,17) (3,18) (4,19) (4,20) (5,21) (5,22) (5,23) (5,24) (5,25) (6,26) (6,27) (6,28) (7,29) (7,30) (7,31) (7,32) (26,33) (26,34) (26,35) (35,36) (35,37) (37,38) (37,39) (37,40) |
| 紧前关系集P | (2,3) (3,4) (4,5) (6,7) (7,8) (8,9) (11,12) (12,13) (15,16) (16,17) (19,20) (21,22) (22,23) (24,25) (26,27) (27,28) (29,30) (31,32) (33,34) (39,40) (28,4) |
| 互斥关系集H | (21,24) (36,37) |
| [1] | 刘一弓, 潘立新, 金晶. 挣值法在航空项目目标成本管理中的应用分析[J]. 航空科学技术, 2016, 27(11): 46-51. |
| Liu Yigong, Pan Lixin, Jin Jing. Research on Implementing Earned Value Method in Aeronautic Project's Target Cost Management[J]. Aeronautical Science & Technology, 2016, 27(11): 46-51. | |
| [2] | 曹建国. 数字化转型下航空发动机仿真技术发展机遇及应用展望[J]. 系统仿真学报, 2023, 35(1): 1-10. |
| Cao Jianguo. Development Opportunities and Application Prospects of Aero-engine Simulation Technology Under Digital Transformation[J]. Journal of System Simulation, 2023, 35(1): 1-10. | |
| [3] | Kim B C. Probabilistic Evaluation of Cost Performance Stability in Earned Value Management[J]. Journal of Management in Engineering, 2016, 32(1): 04015025. |
| [4] | Soltan Sajad, Ashrafi Maryam. Predicting Project Duration and Cost, and Selecting the Best Action Plan Using Statistical Methods for Earned Value Management[J]. Journal of Project Management, 2020, 5(3): 157-166. |
| [5] | Khamooshi H, Abdi A. Project Duration Forecasting Using Earned Duration Management with Exponential Smoothing Techniques[J]. Journal of Management in Engineering, 2017, 33(1): 04016032. |
| [6] | 吉格迪, 杨康. 基于委托代理理论的建设项目多要素协同激励控制模型研究[J]. 工业工程, 2020, 23(1): 96-103. |
| Ji Gedi, Yang Kang. A Multi-factor Cooperative Incentive Control Model of Construction Projects Based on Principal Agent Theory[J]. Industrial Engineering Journal, 2020, 23(1): 96-103. | |
| [7] | 吴诗辉, 解江, 刘晓东, 等. 装备研制项目的模糊挣值管理方法[J]. 航空学报, 2017, 38(2): 254-268. |
| Wu Shihui, Xie Jiang, Liu Xiaodong, et al. Method of Fuzzy Earned Value Management for Weapon Equipment Development Project[J]. Acta Aeronautica et Astronautica Sinica, 2017, 38(2): 254-268. | |
| [8] | 徐梓灵, 刘晓东, 贺波. 基于CPM与风险等级的大型复杂项目模糊挣值管理理论[J]. 数学的实践与认识, 2025, 55(4): 1-16. |
| Xu Ziling, Liu Xiaodong, He Bo. Earned Value Management Theory of Large-scale and Complex Projects Based on CPM and Risk Levels[J]. Mathematics in Practice and Theory, 2025, 55(4): 1-16. | |
| [9] | Cao Ping, Li Danyang, Cao Zhi, et al. Research on Dynamic Optimization of a Critical Path Based on Stochastic Duration and the Earned Value Method[J]. Buildings, 2025, 15(8): 1285. |
| [10] | 陈英, 田娜, 陈夏燕, 等. 基于挣值法的军工科研项目管理实践[J]. 项目管理技术, 2024, 22(12): 160-164. |
| Chen Ying, Tian Na, Chen Xiayan, et al. Practice of Military Research Project Management Based on Earned Value Method[J]. Project Management Technology, 2024, 22(12): 160-164. | |
| [11] | 廖伟, 宁延. 挣值管理在项目完工预测中的应用与改进: 研究综述[J]. 科技管理研究, 2023, 43(11): 185-190. |
| Liao Wei, Ning Yan. Application and Improvement of Earned Value Management in Project Completion Prediction: A Review[J]. Science and Technology Management Research, 2023, 43(11): 185-190. | |
| [12] | 牟强, 贾广社. 改进固定工期大中型工程的完工成本估算[J]. 中国管理科学, 2018, 26(4): 180-187. |
| Mou Qiang, Jia Guangshe. Improving Cost Estimate at Completion of the Duration-fixed Mega Construction Project[J]. Chinese Journal of Management Science, 2018, 26(4): 180-187. | |
| [13] | Zhong Shuheng, Wang Xin. Improvement and Application of Earned Value Analysis in Coal Project Management[J]. Procedia Engineering, 2011, 26: 1983-1989. |
| [14] | Narbaev Timur, Alberto De Marco. Combination of Growth Model and Earned Schedule to Forecast Project Cost at Completion[J]. Journal of Construction Engineering and Management, 2014, 140(1): 04013038. |
| [15] | Bagherpour Morteza, Mohammad Khaje Zadeh, Mahmoudi Amin, et al. Interpretive Structural Modeling in Earned Value Management[J]. Journal of Civil Engineering and Management, 2020, 26(6): 524-533. |
| [16] | 肖依永, 常文兵, 周晟瀚, 等. 现代装备系统经济性工程(理论、方法与应用)[M]. 北京: 科学出版社, 2022: 165-173. |
| [17] | Seyed Taha Hossein Mortaji, Noorossana Rassoul, Bagherpour Morteza. Project Completion Time and Cost Prediction Using Change Point Analysis[J]. Journal of Management in Engineering, 2015, 31(5): 04014086. |
| [18] | Mahmoudi Amin, Bagherpour Morteza, Saad Ahmed Javed. Grey Earned Value Management: Theory and Applications[J]. IEEE Transactions on Engineering Management, 2021, 68(6): 1703-1721. |
| [19] | Setyopurnomo Rudy, Sudarso Kaderi Wiryono, Yuliani Dwi Lestari, et al. Incorporating Earned Value Management Into Income Statements to Improve Project Management Profitability and Elevate Application in the Business and Management[J]. PLoS One, 2025, 20(1): e0312956. |
| [20] | Aramali V, Gibson G E, Sanboskani H, et al. Enhancing Project Success: The Impact of Sociotechnical Integration on Project and Program Management Using Earned Value Management Systems[J]. International Journal of Managing Projects in Business, 2024, 17(8): 1-21. |
| [21] | 赵韩, 武照云, 韦艳丽, 等. 复杂产品开发过程仿真与预测研究[J]. 系统仿真学报, 2009, 21(22): 7350-7354, 7358. |
| Zhao Han, Wu Zhaoyun, Wei Yanli, et al. Research on Complex Product Development Process Simulation and Prediction[J]. Journal of System Simulation, 2009, 21(22): 7350-7354, 7358. | |
| [22] | 王爱文, 曲慧杨, 周军华, 等. 虚拟采办全寿命周期管理技术研究及应用[J]. 系统仿真学报, 2012, 24(10): 2126-2130. |
| Wang Aiwen, Qu Huiyang, Zhou Junhua, et al. Research and Application on SBA Life-cycle Management Technology[J]. Journal of System Simulation, 2012, 24(10): 2126-2130. | |
| [23] | 田畇, 袁莹莹, 曹金龙, 等. 复杂装备研制项目的动态挣值管理与可视化技术[J]. 系统工程, 2014, 32(4): 45-53. |
| Tian Yun, Yuan Yingying, Cao Jinlong, et al. Dynamic EVM and Its Visualization for Complex Equipment Development Projects[J]. Systems Engineering, 2014, 32(4): 45-53. | |
| [24] | Mohammad Reza Hasanzadeh, Behrooz Arbab Shirani, Gholam Ali Raissi Ardali. An Improved Performance Measurement Approach for Knowledge-based Companies Using Kalman Filter Forecasting Method[J]. Mathematical Problems in Engineering, 2016, 2016(1): 4831867. |
| [25] | 詹伟, 杨超. 基于蒙特卡洛模拟和挣值分析的项目完工预测优化[J]. 科技管理研究, 2019, 39(17): 214-219. |
| Zhan Wei, Yang Chao. Optimization of Forecast at Completion Based on Monte Carlo Simulation and Earned Value Analysis[J]. Science and Technology Management Research, 2019, 39(17): 214-219. | |
| [26] | Damavandi Majid, Tavakoli Mahdieh, Jolai Fariborz. Project Cost Forecasting Based on Earned Value Management and Markov Chain[J]. Annals of Operations Research, 2025, 351(1): 1023-1048. |
| [27] | Sackey Solomon, Lee Dong-Eun, Kim Byung-Soo. Duration Estimate at Completion: Improving Earned Value Management Forecasting Accuracy[J]. KSCE Journal of Civil Engineering, 2020, 24(3): 693-702. |
| [28] | Panquet Quentin, Bourgault Mario, Pellerin Robert, et al. A Process-improvement Method for Implementing Earned Value-based Project Management in Organizations[J]. Journal of Construction Engineering and Management, 2024, 150(12): 04024170. |
| [1] | Duan Xinhui, Cheng Zelong, Zhang Dongchao, Duan Xiaochong. Optimal Scheduling of an Integrated Energy System Considering Demand Response and Two-stage P2G [J]. Journal of System Simulation, 2025, 37(8): 2139-2151. |
| [2] | Liu Jiangong, Zhang Yuanhui, Wei Fei, Wang Yiying, Li Xiaoling, Liu Peiqing, Si Fengmiao. Research on Rule-based Energy Management Strategy of Hybrid Mining Dump Truck [J]. Journal of System Simulation, 2025, 37(2): 487-497. |
| [3] | Zhao Baiting, Shi Jianguo, Jia Xiaofen. Research on Digital Twin System of Rockshaft Hoist [J]. Journal of System Simulation, 2024, 36(9): 2054-2064. |
| [4] | Zhenping Li, Ying Shi, Lingyun Wu. Research on Mixed Flow Line Balancing and Scheduling Optimization with Multiple Constraints [J]. Journal of System Simulation, 2023, 35(1): 27-40. |
| [5] | Zhenping Li, Guang Yang, Qianqian Han. Vehicle Routing Problem with Refined Oil Secondary Distribution Considering Workload Balance [J]. Journal of System Simulation, 2022, 34(2): 221-233. |
| [6] | Li Zhenping, Zhao Yuwei, Zhang Yuwei, Xing Lining, Ren Teng. Joint Distribution Location-routing Problem and Large Neighborhood Search Algorithm [J]. Journal of System Simulation, 2021, 33(10): 2518-2531. |
| [7] | Sun Weiqing, Liu Tong, Liu Bo, Wang Youjia. Network Mode and Economy Analysis of Photovoltaic-Battery System in Microgrid [J]. Journal of System Simulation, 2018, 30(5): 1812-1818. |
| [8] | Xiong Zui, Wang Keren, Jin Hu, Feng Hui. Interference Alignment Based Throughput Optimization Model of Multi-hop Networks [J]. Journal of System Simulation, 2015, 27(6): 1240-1246. |
| Viewed | ||||||
|
Full text |
|
|||||
|
Abstract |
|
|||||