复杂项目多级动态挣值管理数字化模型及应用

王伟1, 刘东2, 崔新豪2, 李博2, 肖依永2, 任羿2   

  1. 1.中国航发贵阳发动机设计研究所,贵州 贵阳 550081
    2.北京航空航天大学 可靠性与系统工程学院,北京 100191
  • 收稿日期:2025-04-22 修回日期:2025-06-20 出版日期:2026-05-21 发布日期:2026-05-29
  • 通讯作者: 肖依永
  • 第一作者简介:王伟(1986-),男,工程师,硕士,研究方向为经济性数字化管理与应用。
  • 基金资助:
    国家自然科学基金(72471016);国家自然科学基金委员会?中国民用航空局民航联合研究基金(U2233214)

Multi-level Digital Model of Dynamic Earned Value Management for Complex Engineering Projects and Its Applications

Wang Wei1, Liu Dong2, Cui Xinhao2, Li Bo2, Xiao Yiyong2, Ren Yi2   

  1. 1.AECC Guiyang Engine Design Research Institute, Guiyang 550081, China
    2.School of Reliability and Systems Engineering, Beihang University, Beijing 100191, China
  • Received:2025-04-22 Revised:2025-06-20 Online:2026-05-21 Published:2026-05-29
  • Contact: Xiao Yiyong

摘要:

现有工程项目的经济性管理工作通常基于组织架构开展,针对在复杂工程项目开展时呈现出流程繁杂、主体责任难以明确等问题,提出了一种面向复杂工程项目的多级动态挣值管理数字化模型。将传统的成本绩效指标扩展至工程资源效用维度,把成本的挣得值分解为不同工程资源的挣得值细分,使管理者既能够基于传统的“进度‒成本”绩效指标对项目进行动态监管,还能够面向工程资源的效用水平开展更精细化的成本管控。依据仿真建模架构提出了一种面向动态挣值分析的混合整数规划模型通过求解该仿真优化模型实现了对项目完工时间的实时预测和动态关键路径的准确识别。仿真实验结果表明:该仿真优化模型具有较高求解效率,可满足大规模级别的复杂工程项目需求。基于所提出的动态挣值数字化管理模型,开发了相应的应用软件系统,并应用于某型航空产品的设计研制工程项目,也是挣值管理相关概念理论在国内实际复杂航空产品设计研制场景中的一次重要应用与验证

关键词: 挣值管理, 成本工程, 混合整数规划, 动态关键路径, 经济性, 数字化模型

Abstract:

The economic management of existing engineering projects is usually based on organizational structure, which presents problems such as complex processes and difficulty in clarifying main responsibilities when applied to complex engineering projects. In response to this limitation, a multi-level digital model of dynamic earned value management is proposed for complex engineering projects, which extends the traditional cost performance indicators to engineering resource utility indicators, thereby decomposing the earned value of costs into segmented earned values of different engineering resources. This enables managers to dynamically supervise projects based on traditional "schedule-cost" performance indicators and carry out more refined cost control based on the utility level of engineering resources. Based on a simulation modeling framework,a mixed integer programming model is proposed for dynamic earned value analysis. Real-time prediction of project completion time and accurate identification of dynamic critical paths are achieved through solving the model. Computational experiments show that the model has high solving efficiency and meets the requirements of large-scale complex engineering projects. Based on the proposed digital model of dynamic earned value management, a corresponding application software system is developed and applied to the design and development project of a certain type of aviation product. This is also important application and verification of the concept theory of earned value management in the actual complex aviation product design and development scenarios in China.

Key words: earned value management, cost engineering, mixed integer programming, dynamic critical path, economy, digital model